Lift Installation Process From Site Survey to Handover

The lift installation process step by step: survey, drawings, civil work, supply, installation, testing, registration and handover, with typical timelines.

Add as a preferred source on Google

Know more about this topic with AI

Lift Installation Process From Site Survey to Handover
Key takeaways
  • The lift installation process has ten stages: enquiry, site survey, design, quote and order, civil work, supply, installation, testing, registration and handover with AMC.
  • Civil work (shaft, pit, headroom, machine room or controller space, power supply) is the owner's responsibility and the most common cause of delay.
  • From order to handover, a typical low-rise lift takes somewhere between two and four months, depending mainly on civil readiness and manufacturing time.
  • Insist on final approved drawings before civil work starts, and a written test report before you accept the lift.
  • Plan registration, inspection and maintenance from the start, as rules in Bihar and Uttar Pradesh now cover all three.

The lift installation process runs in ten stages: enquiry, site survey, design and drawings, quote and order, civil work, supply, installation, testing and commissioning, registration and inspection, and finally handover with a maintenance contract. For a typical low-rise building, the whole journey from order to a working lift commonly takes two to four months, and the biggest variable is not the lift company but how quickly the building's civil work is ready. Below, each step is explained with what happens, how long it usually takes and what you, the owner, need to prepare.

The lift installation process at a glance

StepStageTypical timeOwner prepares
1Enquiry1 to 3 daysBuilding type, floors, purpose
2Site survey1 visitAccess, architect's plans, site contact
3Design and drawings1 to 2 weeksDecisions on capacity, doors, finish
4Quote and orderDepends on ownerComparison of quotes, advance payment
5Civil work2 to 8 weeks (runs alongside step 6)Shaft, pit, headroom, machine room, power
6Manufacturing and supply3 to 8 weeksSafe, dry storage space on site
7Installation2 to 4 weeks for low-risePower, water, site access, security
8Testing and commissioning2 to 5 daysPermanent power supply
9Registration and inspectionDepends on authorityOwner documents, applications
10Handover and AMC1 dayStaff for training, AMC decision

These ranges are indicative. Your supplier should give you a project-specific schedule in writing with the quote.

Step 1: Enquiry

You contact the lift company and share the basics: building type (house, apartment, hospital, hotel, shop or warehouse), number of floors, who will use the lift and whether the building exists or is still being designed. A good company will ask questions before quoting a price, not the other way round.

Owner prepares: a rough idea of passengers or load, any space already kept for a lift, and your budget.

Step 2: Site survey

A technical person visits to measure the proposed shaft, check pit depth and top headroom, look at the power supply, and understand how materials will reach the site. In older parts of towns across Bihar and Eastern UP, narrow lanes and shared walls can affect both the lift choice and delivery, so this visit matters.

Owner prepares: architect's or structural drawings if available, access to every floor and the roof, and a person on site who can answer questions.

Step 3: Design and drawings

Based on the survey, the lift company proposes the lift type (traction with machine room, MRL, or hydraulic), capacity, speed, door type and car size. It then issues a general arrangement drawing showing shaft dimensions, pit depth, headroom, machine room or controller location, door openings, hooks and electrical points. If you are short of space, our guide on how much space a home lift needs will help you understand the options.

Owner prepares: decisions on capacity, door type, cabin finish and number of stops. Share the drawing with your architect and structural engineer before anyone starts building.

Step 4: Quote and order

You receive an itemised quotation listing equipment, safety features, civil and electrical work in or out of scope, warranty, AMC terms, payment stages and delivery schedule. Compare quotes on the same specification, not just on price. Our buyer's guide on how to choose a lift company lists the questions to ask.

Owner prepares: a signed order and advance payment, and final confirmation of the drawings. Changing car size or stops after this point can delay manufacturing.

Step 5: Civil work

This is the stage where most projects lose time. The owner's contractor builds or adapts the shaft to the approved drawing. Key items:

  • Shaft: plumb, correct inside dimensions, with openings at each floor of the right width and height.
  • Pit: correct depth below the lowest floor, waterproofed and dry. Seepage during the monsoon is a common problem in low-lying areas.
  • Headroom: correct clear height above the top floor to the shaft ceiling.
  • Machine room or controller space: for traction lifts with a machine room, a ventilated, lockable room with a lifting hook; for MRL lifts, space for the controller near the top landing.
  • Hooks and anchors: fixed where the drawing shows, rated for lifting the machine.
  • Power: a dedicated supply to the machine area with isolator and proper earthing, plus a separate lighting circuit.

Owner prepares: a contractor who follows the drawing exactly. Ask the lift company to inspect the shaft before it is plastered and again before installation.

Step 6: Manufacturing and supply

Once drawings are final, the lift company arranges the car, doors, rails, machine, controller, V3F drive and safety components. Supply time depends on the lift type and finish. Material arrives on site in stages or as one consignment.

Owner prepares: a secure, dry storage area close to the shaft. Rails, doors and controllers must not be left out in rain or dust.

Step 7: Installation

The installation team works through a fixed sequence:

  1. Set plumb lines and check the shaft.
  2. Fix rail brackets and erect car and counterweight guide rails.
  3. Install the machine (in the machine room, the shaft head for MRL, or the power unit for hydraulic).
  4. Assemble the car frame, platform, cabin and car door.
  5. Install landing doors, frames and door locks at every floor.
  6. Fit ropes or belts (or cylinder and hoses for hydraulic), counterweight and buffers.
  7. Run shaft wiring and connect the controller, drive, safety circuit and car fixtures.

Eldeal carries out an inspection at each installation stage rather than only at the end, so faults are caught while they are easy to correct. Find out more about our lift installation service.

Owner prepares: temporary power and lighting, restricted access to the shaft area, and no other trades working in the shaft at the same time.

Step 8: Testing and commissioning

Before the lift carries anyone, every function and safety device is tested. A proper commissioning checklist includes:

  • door interlocks and car door contact at every floor;
  • overspeed governor and safety gear;
  • buffers and final limit switches;
  • UCMP and ACOP devices where fitted (new lifts built to IS 17900 emphasise both);
  • ARD operation with mains power switched off;
  • overload sensor and voice prompt;
  • light curtain, alarm, intercom and emergency light;
  • levelling accuracy and ride comfort at every floor.

Owner prepares: the permanent power supply connected and stable. Ask for the signed test report.

Step 9: Registration and inspection

IS 17900, the Indian lift safety standard harmonised with EN 81-20 and EN 81-50, became mandatory for new installations from 22 December 2025 according to BIS. State laws add registration and inspection:

  • The Uttar Pradesh Lifts and Escalators Act, 2024 requires lifts and escalators to be registered and regularly maintained.
  • The Bihar Lift and Escalator Bill, 2024, passed by the Bihar Assembly on 2 August 2024, covers registration, inspections, mandatory maintenance and third-party insurance.

Procedures, forms and fees are set by the state authority and can change, so confirm the current requirements locally before handover.

Owner prepares: ownership documents, building details and any application the authority requires. Your lift company can guide you on the technical documents.

Step 10: Handover and AMC

At handover, the lift company demonstrates the lift, trains your staff on the alarm, intercom and basic rescue procedure, and hands over documents: test report, warranty, manuals, wiring diagrams and emergency keys. This is also when maintenance begins. Most lifts need monthly preventive service; our lift maintenance checklist shows what should be covered, and an annual maintenance contract keeps it on schedule.

Owner prepares: named staff for training, a safe place for emergency keys and a decision on the AMC.

Common causes of delay and how to avoid them

CauseHow to avoid it
Shaft built to wrong size or out of plumbBuild only to approved drawings; ask for a shaft check before plastering
Pit too shallow or wetConfirm pit depth early; waterproof before the monsoon
Specification changed after orderFreeze car size, stops and doors before manufacturing starts
Permanent power not readyApply for the connection early; testing needs a stable supply
Other trades working in the shaftHand over the shaft to the lift team only

Questions to ask before installation starts

  1. Have the final drawings been approved by my architect and structural engineer?
  2. Which civil and electrical items are in my scope, and which are in yours?
  3. When will you inspect the shaft, and what tolerance do you accept?
  4. What is the written schedule from order to handover, and what could change it?
  5. Which safety tests will be in the commissioning report?
  6. Who will help with registration and inspection paperwork?

Clear answers to these questions at the start save weeks later. If a supplier cannot answer them in writing, treat that as a warning sign.

Start your lift project with a free survey

Eldeal Engineers handles the full lift installation process for homes, apartments, hospitals, hotels and commercial buildings across Bihar, Eastern UP and Delhi NCR, from offices in Sasaram, Patna, Varanasi and Bhagalpur. We give you clear drawings, an itemised quote and a written schedule before any work begins. Book a free site survey or ask for an AMC quote: call or WhatsApp +91 84489 44342 or +91 62077 91650.

Found this guide useful?

Add Eldeal Engineers as a preferred source to see more of our guides on Google.

Add as a preferred source on Google

Know more about this topic with AI

Open this article in your AI assistant and ask your follow-up questions.

FAQ

Frequently asked questions

Still have a question? Call +91 8448944342 or +91 6207791650

How long does the lift installation process take?

For a typical low-rise passenger or home lift, allow roughly two to four months from confirmed order to handover. Manufacturing and supply often take a few weeks, and on-site installation of a low-rise lift commonly takes two to four weeks once the shaft is ready. Unfinished civil work is the biggest cause of delay.

Who is responsible for building the lift shaft?

Usually the building owner, through their own contractor, following the lift company's approved drawings. The lift company specifies shaft size, pit depth, headroom, hooks, openings and power points, and should visit to check the work before installation starts.

Can a lift be installed in an existing building?

Often yes. Options include cutting slabs for a new shaft, using a stairwell or courtyard, or building an external steel structure. An MRL or hydraulic lift can help where there is no space for a machine room. A site survey tells you which route works for your building.

What electrical supply does a lift need?

Most passenger lifts need a dedicated three-phase supply with a separate isolator, correct earthing and a separate light and socket circuit for the shaft and machine area. Small home lifts may work on single-phase. Your lift company will specify the exact load and cable size in the drawings.

Can I use the lift before the final inspection?

You should not open a lift for public or regular use until it has been fully tested and handed over, and any registration or inspection required in your state has been completed. Check the current rules with your state lift authority.

What documents should I receive at handover?

The test and commissioning report, warranty terms, operation and rescue manuals, wiring diagrams, emergency landing door keys for trained staff, and details of the maintenance contract and 24/7 contact number.

Keep reading

Related guides.

Top 10 Lift Companies in Uttar Pradesh (2026)
Buying Guides 8 min read

Top 10 Lift Companies in Uttar Pradesh (2026)

Ten lift companies in Uttar Pradesh with offices we could verify, city by city, from Noida and Lucknow to Varanasi, plus what the UP lift…

Top 10 Lift Companies in Varanasi (2026)
Buying Guides 8 min read

Top 10 Lift Companies in Varanasi (2026)

Ten lift companies in Varanasi with a presence we could verify: local firms, national brands with a Varanasi office, and how to compare…

Free consultation

Get a free site survey & quote

Tell us about your building. An engineer will call you back — usually the same day — with honest advice and a transparent quote.

Request a call back

We reply fast. No spam — your details are only used to answer your enquiry. Privacy

Protected by reCAPTCHA — Google Privacy & Terms apply.